Repairs done to Selkie are listed here.  I've done all the work myself, except for fabrication of the new rudder.

 

2002

Large Projects
Electric Bilge pump
    Design, Fabricate and wire all new Installation

Head
    Design and install all new Head, Pumpout and Holding Tank

Water Tank
    Repair Tank/Install Inspection Port
    Replace all Hoses

Replacements
Cockpit Cleats
Bilge Blower
Stern Light
Deck Vents at stern
Cabin Light
Propeller Shaft and Cutlass Bearing
Bow Vent
Cushion Foam
Anchor Rode

Maintenance
Reinforce Transom/ Reinstall OB Mount w/ standoffs
Refinish Tiller/Install Hiking Stick
Rewire Horn
Rewire Bow Lights
Partial Rewire of Mast Lighting
Remove Old Wiring and Redundant Equipment
Rebed some deck fittings

New Additions
Barometric Instruments
Spare Anchor and Rode

 

2003

Large Projects
Instrument Panel
            Design/Fabricate/Install/Wire new Panel
            Install new senders

Centerboard
            Design/Fabricate/Install new lifting tackle
            Grind out and repair damaged head

Rudder
            Remove/Fabricate/Replace Rudder Tube
            Replace Rudder

Running Rigging
            Fabricate and Replace all

Replacements
Backstay
Lifelines
Lifeline Stanchion
Stove
Spreaders
Fuel Pump
Propeller
Tiller 

Maintenance
Rebuild Carburetor
Repair Genoa

 

2004

Large Projects

Design/replace entire fuel system –
        Stringers, tank, filler neck, filter, valve, upgraded fuel pump

Replacements
Manual Bilge Pump
Genoa
Transmission Shift Cable
Life-ring
Topping lift
Masthead Light
Steaming Light
Dorade Vents
Boathook

Maintenance
Re-route and Partial Replacement of Cooling System Hoses
Re-route and Partial Replacement of Exhaust Hose
Work on Mast Partners
Rename boat
Modify engine air vent/cooling bypass to stabilize temperature control (unsuccessful)

New Additions
Autopilot
Solar Battery Charger